Burgau Sea Gardens October 2024 Construction Update

Significant progress continues at the Burgau Sea Gardens development. Below is the latest status of construction across the site:

Block A

Current works focus on the installation of false ceilings and interior painting. All exterior window frames have been fully installed.

Block B

Interior works are in progress, with the painting, and installation of interior doors, wardrobes, kitchens, and sanitary equipment underway. Exterior works have been completed, including installing window frames and shutters.

Block C

Interior wall and ceiling coverings are being installed. As with the other blocks, exterior framing has been completed.

Exterior Works

The pool structure and external sewage and drainage systems have been completed. Foundation work for the reception area has now begun.

Further updates will follow as construction progresses. For more information about the project, please visit: Burgau Sea Gardens

For more information, or to schedule a viewing, please contact our preferred agent, ten Hoopen Realty

Phone: +351963766261

Emailsales@tenhoopenrealty.com

Share this article

If you like this article, please share it, thanks

Facebook
Twitter
LinkedIn
WhatsApp
Email